To improve the indoor climate and energy efficiency, insulation was both added and repaired around the perimeter of the facility. The insulation covering all of the walls was then cleaned by a professional cleaning company.
The indoor courts are closed for renovation. All outdoor courts are open today weather pending.
Construction Schedule
May 21 Clay removal begins May 29-30 Steel repair work June 4-15 Steel coating and electrical upgrades June 18 New court construction begins July 2-20 Cleaning, painting, and insulation August 1First layer Deco applied August 9Tennis "Happy Hour" 6-8 pm
August 24 Final paint coats applied
August 31 Tentative grand reopening